If the SPI and CPI are both above 1, then the project is:
A.
Ahead of schedule and over budget.
B.
Ahead of schedule and under budget.
C.
Behind schedule and over budget.
D.
Behind schedule and under budget.
If the SPI and CPI are both above 1, then the project is:
If the SPI and CPI are both above 1, then the project is:
A.
Ahead of schedule and over budget.
B.
Ahead of schedule and under budget.
C.
Behind schedule and over budget.
D.
Behind schedule and under budget.