If the SPI and CPI are both above 1, then the project is:

If the SPI and CPI are both above 1, then the project is:

If the SPI and CPI are both above 1, then the project is:

A.
Ahead of schedule and over budget.

B.
Ahead of schedule and under budget.

C.
Behind schedule and over budget.

D.
Behind schedule and under budget.