Which of the following is a document used iteratively during a project to capture strengths
and weaknesses?
A.
SWOT analysis
B.
Quality plan
C.
Scope document
D.
Lessons learned
Which of the following is a document used iteratively during a project to capture strengths
and weaknesses?
Which of the following is a document used iteratively during a project to capture strengths
and weaknesses?
A.
SWOT analysis
B.
Quality plan
C.
Scope document
D.
Lessons learned
I believe this is A. Lessons learned is at project closure