A project has been going on for three weeks, and the project manager notices that
Resource A is beginning to fall behind schedule. The project manager should FIRST
schedule a meeting with:
A.
The project stakeholders to communicate the delay.
B.
Resource A to confirm estimates.
C.
The other team members to make up the schedule slippage.
D.
The manager of Resource A for corrective action.