A project has two resources scheduled to work 40 hours a week for four weeks, both at
$85.00 an hour. One resource called in sick for 16 hours, while the other resource worked
four hours additional. Which of the following is the cost of the resources?
A.
$27,540
B.
$25,840
C.
$26,180
D.
$27,200
Explanation: