Which of the following is the BEST response?

A project team is meeting monthly for their project risk review. During the brainstorm, one of
the team members mentions that a risk to the project could be a delay with the servers.
Which of the following is the BEST response?

A project team is meeting monthly for their project risk review. During the brainstorm, one of
the team members mentions that a risk to the project could be a delay with the servers.
Which of the following is the BEST response?

A.
Avoid

B.
Enhance

C.
Exploit

D.
Share