Which of the following conclusions is correct?

A project manager has calculated their project to have a SV of -$5,000. Which of the
following conclusions is correct?

A project manager has calculated their project to have a SV of -$5,000. Which of the
following conclusions is correct?

A.
The project is behind schedule

B.
The project is under budget

C.
The project is over budget

D.
The project baseline is incorrect