The project has spent $5,000 to date. The earned value of the project is $7,500. Which of
the following is the project’s CPI?
A.
-$2,500
B.
$12,500
C.
0.67
D.
1.5
The project has spent $5,000 to date. The earned value of the project is $7,500. Which of
the following is the project’s CPI?