A project is having issues because the time required to do the smaller work items in the
project were underestimated. This could have been avoided by using:
A.
A budget
B.
A scope statement
C.
AWBS
D.
Quality metrics
A project is having issues because the time required to do the smaller work items in the
project were underestimated. This could have been avoided by using: