Stakeholders have submitted change requests via email, telephone calls, stopping by,
during meetings, and using the change request form. Also, once the change request is
made, the stakeholders expect the request to be immediately acted upon. Which of the
following can be produced to aid in the stakeholders’ understanding of how change control
is performed on the project?
A.
Stakeholder register
B.
Process flow diagram
C.
Work breakdown structure
D.
Issue log