The BEST time to communicate stakeholder expectations to the project team is:

The BEST time to communicate stakeholder expectations to the project team is:

The BEST time to communicate stakeholder expectations to the project team is:

A.
During the project kick-off meeting.

B.
During the development of the work breakdown structure.

C.
During bi-weekly status meetings.

D.
At regular intervals as defined in the communications management plan.