Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most
Likely = 4 days, calculate PERT.
A.
8 days
B.
6 days
C.
4 days
D.
5 days
Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most
Likely = 4 days, calculate PERT.