Given the schedule estimates of Best Case = 2 days…

Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most
Likely = 4 days, calculate PERT.

Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most
Likely = 4 days, calculate PERT.

A.
8 days

B.
6 days

C.
4 days

D.
5 days