Which of the following would the project manager do to help determine the root cause of the budget overrun?

A project manager has inherited a project that is $5 million over budget. Which of the
following would the project manager do to help determine the root cause of the budget
overrun?

A project manager has inherited a project that is $5 million over budget. Which of the
following would the project manager do to help determine the root cause of the budget
overrun?

A.
Ensure the project plan reflects all tasks were documented during planning

B.
Review the change control log

C.
Perform qualitative risk analysis

D.
Review if the project has maintained alignment with the scope