During customer acceptance, a project manager meets with the stakeholders who claim a
bridge was built with two toll gates instead of three. Which of the following documents would
clarify the discrepancy?
A.
Risk Management Plan
B.
Closeout report
C.
Scope Statement
D.
Lessons Learned