A team member has approached the project manager for an update on the project status
and next tasks. Which of the following should the project manager do NEXT?
A.
Speak with the team member’s manager about their performance
B.
Resend the latest status report and project plan to the team member
C.
Review the communications plan to determine why they were unaware
D.
Send the communications plan to the team member