A change request has been submitted to the project manager containing the date, the
details of the request, and the impact to the project. Which of the following needs to
accompany the change request before it can be reviewed for consideration?
A.
Customer acceptance
B.
Stakeholder sign-off
C.
Alternative options
D.
Requirements document