In which of the following areas would a transition plan be used?
A.
When the project manager is added to the project and the project authority shifts to their
responsibility
B.
As a project phase is completed and the project shifts to a new phase
C.
At the end of the project to transfer maintenance responsibilities
D. After the project receives approval and becomes an active project
C.
At the end of the project to transfer maintenance responsibilities