which of the following areas would a transition plan be used?

In which of the following areas would a transition plan be used?

In which of the following areas would a transition plan be used?

A.
When the project manager is added to the project and the project authority shifts to their
responsibility

B.
As a project phase is completed and the project shifts to a new phase

C.
At the end of the project to transfer maintenance responsibilities

D. After the project receives approval and becomes an active project



Leave a Reply 1

Your email address will not be published. Required fields are marked *


pzhar

pzhar

C.
At the end of the project to transfer maintenance responsibilities