A WBS dictionary:
A.
allocates the WBS components to appropriate teams or named individuals within teams.
B.
describes how a project will be decomposed into smaller, manageable subprojects or
work packages.
C.
provides a description of all of the components of a WBS, and a brief summary of its
SOW, scope and deliverables.
D.
is a granular hierarchical breakdown of the work to be undertaken by the project team, to
meet the objectives of the project.
Explanation: