Which of the following is the BEST method to avoid staffing conflict between resource
managers and project managers?
A.
Ask the project sponsor for team member assignments.
B.
Claim the best department resources before the project starts.
C.
Formally request team members early.
D.
Allow team members to enter the project as best fits their schedule.