The project manager has received an approved change request. Which of the following
actions should the project manager take NEXT?
A.
Develop a plan to incorporate the change into the project
B.
Schedule a meeting with the change advisory board to discuss the impact of the change
C.
Perform a probability and impact assessment on the approved change
D.
Hold a team meeting to ensure the change is immediately implemented