Which of the following is created using the work breakdown structure (WBS) as an input?

Which of the following is created using the work breakdown structure (WBS) as an input?

Which of the following is created using the work breakdown structure (WBS) as an input?

A.
Procurement management plan

B.
Vendor selection criteria

C.
Project scope statement

D.
Project charter