A product has been sent to an outside vendor for testing. During their testing it was determined that the product is not meeting the quality standards. The project manager scheduled a meeting to review their findings. Which of the following BEST describes this situation?
A.
Quality assurance
B.
Quality control
C.
Quality analysis
D.
Quality planning