Which of the following should be created in the project closing documentation? (Select TWO)

Which of the following should be created in the project closing documentation? (Select TWO).

Which of the following should be created in the project closing documentation? (Select TWO).

A.
Closure report summarizing costs

B.
Responsibility assessment matrix

C.
Lessons learned

D.
Project timeline

E.
Statement of Work (SOW)



Leave a Reply 0

Your email address will not be published. Required fields are marked *