Two of the stakeholders cannot agree on the project timeline or budget. The project is critical to the success of the company. Which of the following actions should the project manager take NEXT?
A.
Invite all of the stakeholders to a meeting to discuss project requirements.
B.
Document the points of agreement and create the timeline and budget based upon the expectations of the majority of the stakeholders.
C.
Modify the project scope to bring it into alignment with the stakeholders expectations.
D.
Inform the stakeholders that the project will be cancelled if they cannot agree.