Which of the following BEST describes the situation?

Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation?

Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation?

A.
Varying work styles

B.
Schedule variance

C.
Scope creep

D.
Competing resource demands



Leave a Reply 0

Your email address will not be published. Required fields are marked *