A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?
A.
Move some of the task to another release.
B.
Have the team work over time and give them time off later to save the budget.
C.
Continue to work and complete the project as soon as possible.
D.
Review the plan with the team and develop a way to reduce the time