Given the following information: Pessimistic estimate is 30 days Most Likely estimate is 15 days Optimistic estimate is 10 days. Which of the following is the expected duration for this scheduled activity?
A.
11 days
B.
17 days
C.
25 days
D.
29 days
Equation is O + M4 + P / 6
O = Optimistic
P = Pessimistic
M = Most likely
Can somebody provide some feedback about the validity of this dump? Is it accurate? Are these the questions on the actual test? Thank you