Which of the following is the method for determining the critical path of a project?
A.
Determine the BAC of a project and the AC at completion; calculate the difference.
B.
Examine the project schedule and determine the two most critical milestones; then calculate the total time from the start of the first determined milestone to the end of the second.
C.
Examine the project schedule and place all scheduled activities on one time-line, regardless as to whether they are being implemented in parallel. Then calculate the total time taken.
D.
Examine the project schedule and calculate the total time taken for all scheduled activities, from commencement of the project to closure, with zero float.
Finally passed the PK0-004 exam few days ago!!!
Scored 8xx/900 (the passing score is 710/900 now).
I had 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.
Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.
Also, many questions on Communication and Change Management (about 20%).
Learning the topic of “Project Tools & Documentation” carefully, questions about it are a little difficult.
And, I do recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.
Here, you can get the PL PK0-004 dumps for free:
http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps
Wish you all pass the CompTIA Project+ PK0-004 exam easily!! Good Luck!!!