Which of the following are characteristics of a projects critical path? (Select TWO)

Which of the following are characteristics of a projects critical path? (Select TWO).

Which of the following are characteristics of a projects critical path? (Select TWO).

A.
The critical path is the longest duration.

B.
The critical path has the least amount of resources.

C.
The critical path is the shortest duration.

D.
The critical path has less than or equal to zero float time.

E.
The critical path has a greater than zero float time.



Leave a Reply 1

Your email address will not be published. Required fields are marked *

one × 2 =


Le Fabros

Le Fabros

Congratulations!!

Completed the CompTIA Project+ PK0-004 exam last week!!!

Scored 8xx/900 (the passing score is 710/900 now).

I had 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.

Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.

Also, many questions on Communication and Change Management (about 20%).

Pay close attention to “Project Tools & Documentation”, a little difficult.

And, I do recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.

Here, you can get the PL PK0-004 dumps for free:

http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps