Which of the following is the NEXT step the project manager should take?

A new critical requirement has been identified after the project charter was approved. Which of the following is the NEXT step the project manager should take?

A new critical requirement has been identified after the project charter was approved. Which of the following is the NEXT step the project manager should take?

A.
Convene another meeting with the entire group reviewing the requirements one last time and incorporating the additional requirement.

B.
Determine the effort of the missing requirement and incorporate it into the work plan.

C.
Revise the approved requirements document and forward to the project team for review.

D.
Generate a change request and submit it to the change control board for review.



Leave a Reply 1

Your email address will not be published. Required fields are marked *

20 − nine =


Le Fabros

Le Fabros

Hi! Congrats!! Cleared the CompTIA Project+ PK0-004 exam recently!!!

Scored 8xx/900 (the passing score is 710/900 now).

I had 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.

Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.

Also, many questions on Communication and Change Management (about 20%).

Pay close attention to “Project Tools & Documentation”, a little difficult.

And, I do recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.

Here, you can get the PL PK0-004 dumps for free:

http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps

Good Luck!!!