Which of the following is a characteristic of a project charter?
A.
Issued by the project manager with support from the project sponsor.
B.
Links the project to the on-going work of the organization through a business plan.
C.
Formally recognizes the existence or establishment of the project.
D.
Provides low-level requirements for the project.
Well Done!!! Passed the CompTIA Project+ PK0-004 exam SEVERAL days ago!!!
Scored 8xx/900 (the passing score is 710/900 now).
I had 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.
Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.
Also, many questions on Communication and Change Management (about 20%).
Pay close attention to “Project Tools & Documentation”, a little difficult, I lost points in this section.
And, I do recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.
Here, you can get the PL PK0-004 dumps for free:
http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps
Wish you pass the CompTIA Project+ PK0-004 exam easily!!!