To ensure the quality of implemented project change requests, which of the following will need to occur? (Select TWO).
A.
The project team is not notified of the approved change.
B.
Change is tracked and is either accepted or rejected by the change control board.
C.
Change is logged and updated in the change log document.
D.
Once a change is forwarded to the change control board, it will be removed from the change log.
E.
Once the change is submitted to the change control board, it will be approved and placed into production.