Crashing a schedule involves which of the following?
A.
Performing a re-baseline of the project schedule
B.
Performing critical path activities simultaneously
C.
Adding resources to critical path activities
D.
Estimating the earned value of the project activities
Well Done!!!
Cleared the CompTIA Project+ PK0-004 exam few days ago!!!
Scored 8xx/900 (the passing score is 710/900 now).
I had 95 questions (THE Maximum~~~LOL), including many MCQs and fill in the blank questions.
Around 30% questions are on Project Basics (Summarize, Classify, Compare and contrast…etc.), the primary knowledge of the Project+.
Also, many questions on Communication and Change Management (about 20%).
Pay close attention to “Project Tools & Documentation”, a little difficult, I lost points in this section.
And, I do recommend you to use the PassLeader PK0-004 dumps for preparing for the test, all questions are from it.
Here, you can get the PL PK0-004 dumps for free:
http://www.comptiadump.com/category/comptia-project-plus-certification/pk0-004-dumps
Wish you pass the CompTIA Project+ PK0-004 exam easily!!
Good Luck!!!