Which of the following steps should be taken to formally close a project? (Select TWO).
A.
Finalize the project charter
B.
Create a statement of work (SOW)
C.
Verify client sign-off of the project deliverables
D.
Document the lessons learned
E.
Finalize the work breakdown structure (WBS)