Three factors affect every project, and when one factor is adjusted, it affects the others. This
relationship is known as the Project Triangle. What are the three factors in the Project Triangle?
A.
Gantt charts, tracking and documentation
B.
Testing, evaluating and controlling
C.
ROI, quality and stakeholders
D.
Time, money and scope