Which process requires the Process Supply Chain Orchestration Interface process to be executed manually so
that a supply order gets created?
A.
Planned Order Releases
B.
Drop Shipment
C.
Back-to-Back Procurement
D.
Back-to-Back Contract Manufacturing
E.
Min-Max planning replenishing a purchase request
Explanation:
Needs to be run manually for Inventory MINMAX
https://docs.oracle.com/cloud/latest/scmcs_gs/FAIMS/FAIMS1922443.htm#FAIMS1922441
source please ?
E:
Process Supply Chain Orchestration Interface:
◦Creates supply orders based on Supply Chain Orchestration Interface records
◦Runs automatically for Oracle Fusion Distributed Order Orchestration and Planning
◦Needs to be run manually for Inventory MINMAX