Your company wants to notify the external system when there is a high possibility that an order is going to be
delayed.
Which four steps are required to invoke the external system connector to notify that an order is going to be
delayed? (Choose four.)
A.
Set up the Jeopardy threshold for the orchestration process task.
B.
Set up the lead time for the orchestration steps in the orchestration process definition.
C.
Register the web service connector.
D.
Create a routing rule for the orchestration process task.
E.
Enable a business event trigger point for Jeopardy and associate the connector.
F.
Set up the Use Defined Lead time in the Available To Promise Rule.
Explanation:
https://docs.oracle.com/cloud/latest/scmcs_gs/FAIOM/FAIOM2061950.htm#FAIOM2061950
source please ?
why not C Register Web Service connector instead of B?
rashi, can you please update the reference?
I think ans B stays – Refer- https://fusionhelp.oracle.com/helpPortal/faces/AtkHelpPortalMain?TopicId=1B7A61788AEE2656E05362C3F00AE4AF&_afrLoop=32025369360788456&_afrWindowMode=0&_afrWindowId=null&_adf.ctrl-state=1azyp3io3i_1&_afrFS=16&_afrMT=screen&_afrMFW=1670&_afrMFH=781&_afrMFDW=1670&_afrMFDH=939&_afrMFC=8&_afrMFCI=0&_afrMFM=0&_afrMFR=110&_afrMFG=0&_afrMFS=0&_afrMFO=0
Search for –
Defining Jeopardy and Lead Time to Manage Delay: Procedure
on above link …