As an implementation consultant, you are required to define a total compensation statement. To construct the
total compensation statement, you must follow a set of activities in sequence.
Select the correct sequence to construct a total compensation statement. (Choose the best answer.)
A.
Create compensation items > attach the items to compensation categories > arrange categories
hierarchically in the statement definition > specify the statement period and display options > generate the
statement.
B.
Create compensation items > specify the statement period and display options > arrange categories
hierarchically in the statement definition > attach items to compensation categories > generate the
statement.
C.
Create compensation items > generate a statement > specify the statement period and display options >
arrange categories hierarchically in the statement definition > attach items to compensation categories.
D.
Create compensation items > attach the items to compensation categories > generate the statement >
specify the statement period and display options > arrange categories hierarchically in the statement
definition.