What two actions could you perform to help achieve this result?

Your ten month-long project has been underway for six months, but it needs to be accelerated so
that all project objectives are met a month earlier than originally planned. What two actions could
you perform to help achieve this result? (Choose two.)

Your ten month-long project has been underway for six months, but it needs to be accelerated so
that all project objectives are met a month earlier than originally planned. What two actions could
you perform to help achieve this result? (Choose two.)

A.
Assess the timing and resource assignments for riskiest tasks, then put extra resources on
those activities.

B.
Prepare presentations for the senior executives, focusing on the project accomplishments since
the start of the project.

C.
Ensure that project and task objectives are clear, measurable, and communicated to all
members of the team.

D.
Organize a project team meeting to explain that new or changed requirements will be rejected.

E.
Gain sponsor agreement to make decisions within three days of receiving the request for
approvals.

F.
Conduct design reviews to identify where off-the shelf software can be used instead of the
currently planned custom development.