What should you modify in the Task Information window?

You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?

You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?

A.
Set the Deadline date field.

B.
Set the Constraint date field.

C.
Set the Finish date field.

D.
Select the Mark task as milestone check box.

E.
Select the Display on Timeline check box.

Explanation:
Deadline dates don’t usually affect task scheduling. They are used to indicate a target date you don’t want to miss, without requiring you to set a task constraint that could affect scheduling if predecessor tasks change. A task with a deadline is scheduled just like any other task.