What should you do?

The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?

The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?

A.
Select the Project Summary Task option.

B.
Select the Summary Tasks option.

C.
Create a manually scheduled summary task.

D.
Update the project calendar.



Leave a Reply 0

Your email address will not be published. Required fields are marked *