The project you manage has only part-time resources. The part-time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? Each correct answer presents part of the solution.
A.
Select the part-time calendar from the Change Working Time window.
B.
Set the calendar type to part-time for all tasks.
C.
Select the part-time calendar from the Project Information window.
D.
On the Project tab, Select Change Working Time, and then click Create New Calendar.
E.
Change the Calendar type in the Project Options dialog box.