You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A.
Create a task dependency from Task 4 to Task 6.
B.
Set Task 4 as critical.
C.
Add a 1 day lead to Task 4.
D.
Set Task 4 as manually scheduled.
Explanation:
The Gantt bar for task 6 indicates that it is a manually scheduled task.