You use Project Professional 2010 to manage a software development project as shown in the exhibit.
You need to cancel the ‘Develop prototype based on functional specifications’ task. You also need to retain all the information from the task. Which two actions should you perform? Each correct answer presents part of the solution.
A.
Delete the task.
B.
Set the tasks remaining work to 0 hours.
C.
Inactivate the task.
D.
Make the task 100 percent complete.
E.
Create a link from the ‘Develop functional specifications’ task to the ‘Review functional specifications’ task.