Which set of values describes the task?

One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?

One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?

A.
The task is early by 14 days.

B.
The task is early by 4 days.

C.
The task is late by 4 days.

D.
The task is late by 14 days.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Milind

Milind

The task is late by 4 days.