You need to create a new project schedule by using tasks from an existing project. You need to achieve this goal without inheriting actual hours from the existing project. What would you do first?
A.
On the File menu in Project 2010, use one of the existing templates.
B.
Save the task list in Microsoft Excel and use the Project Import Wizard.
C.
Open the previously saved project schedule and save it as a template.
D.
Save the task list as a Microsoft Excel template.
Explanation:
When you save a project as a template, you can remove baseline data, actuals, resource pay rates, fixed cost information, and task publishing status.