What should you do?

You need to ensure that when you add new tasks, the project schedule doesn’t set a start date and end date. What should you do?

You need to ensure that when you add new tasks, the project schedule doesn’t set a start date and end date. What should you do?

A.
Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.

B.
On the Schedule tab of the Project options, change the ‘New tasks created’ option to Manually Scheduled.

C.
On the Advanced tab of the Project options, clear the Automatically add new resources and tasks check box.

D.
On the Display tab of the Project options, clear the Edits to start and finish dates check box.

E.
Click New Tasks and change the option to Auto Scheduled.

Explanation:
When a task is in manually scheduled mode, the Start, Finish, and Duration columns can be blank.