What should you do?

You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

A.
Select the Gantt Chart view, split the window, and then select the Resource Usage view for the details pane.

B.
Select the Team Planner view.

C.
Select the Timeline view.

D.
Select the Gantt Chart view, and then click Assign Resources.