What should you do?

You create several new tasks by using the Manually Scheduled Task option. You need to automatically calculate the start and finish dates for linked manually scheduled tasks. You need to achieve this goal while retaining manually scheduled tasks within the project. What should you do?

You create several new tasks by using the Manually Scheduled Task option. You need to automatically calculate the start and finish dates for linked manually scheduled tasks. You need to achieve this goal while retaining manually scheduled tasks within the project. What should you do?

A.
Modify the values of Scheduled Start and Scheduled Finish.

B.
Highlight the Project Summary task and use the Calculate Project feature.

C.
Insert the task Constraint Type column and change the values for each task to the appropriate values. Then, recalculate the project.

D.
Use the Respect Links feature.



Leave a Reply 0

Your email address will not be published. Required fields are marked *