What should you do?

You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?

You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?

A.
Create shift resource departments.

B.
Change the maximum units for each resource.

C.
Create three tasks, one for each shift.

D.
Create a base calendar for each shift.



Leave a Reply 0

Your email address will not be published. Required fields are marked *