What should you do?

Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?

Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?

A.
Create cost tables to include rates that activate on effective dates.

B.
Change the resource availability settings to establish Units for selected dates.

C.
Create resources that include fixed Standard costs, and then apply a rate variance per project task.

D.
Create a named resource for each Standard hourly rate.



Leave a Reply 0

Your email address will not be published. Required fields are marked *